Orca EnergyORCA ENERGYCLEAN Energy for the Future

Rooftop solar procedure under Decree 58/2025 in Vietnam

Procedure

Decree 58/2025/ND-CP details provisions of the Electricity Law on renewable energy development and includes a dedicated chapter on self-production, self-consumption rooftop solar; Decree 243/2026/ND-CP later amended parts of it. This guide summarises the sequence based on guidance published by MOIT.

01

Building conditions before installation

According to MOIT guidance at implementation conferences, the host building must have valid construction legal status; adding a rooftop system must not conflict with the building records and must maintain structural, electrical and fire safety.

  • Legally built structure with a roof — or a house-like structure — able to carry the array.
  • System capacity matched to on-site electricity demand.
  • Respect the voltage level and current limits of existing metering equipment.
  • Electrical safety, lightning protection and fire safety documents updated for the added scope.

Decree 243/2026/ND-CP widened the scope to systems installed on structures shaped like a house, not only on roofs of conventional buildings.

02

Notification or development registration: pick the right route

Depending on capacity and whether the system connects to the grid or exports, it may only require a notification or may need development registration with the competent authority. Identify this at design stage because it drives the schedule.

Five-step workflow for self-consumption rooftop solar under Decree 58/2025: survey and design, development registration, grid-connection agreement, installation and testing, commissioning and the 20% surplus cap
The procedural sequence and the energy path: on-site demand is served first, only the surplus passes the meter towards the grid.
  • Step 1 – Survey the roof, measure load, set capacity and decide whether any export is allowed.
  • Step 2 – Determine the applicable route (notification or development registration) by capacity and connection mode.
  • Step 3 – Contact the local power utility for connection and operating guidance.
  • Step 4 – Build, test, commission and complete operating documentation.
  • Step 5 – Archive legal records, acceptance reports and generation data for later reporting.

Exact capacity thresholds and document lists depend on the legislation and on local utility guidance; verify them before starting.

03

Surplus electricity and export limits

The policy direction prioritises on-site consumption and limits export. At the implementation event in Bac Ninh, a MOIT representative stated that self-production, self-consumption systems may sell surplus electricity up to 20% of generated output under the applicable rules.

  • Non-exporting systems typically use zero-export devices and load-following control.
  • Systems selling surplus must agree terms with the power utility and stay within the regulated limit.
  • Adding storage absorbs surplus instead of exporting it, which suits plants with shifted load.
Commercial-Industrial Rooftop Solar Systems in Viet Nam — GIZ Energy Support Programme Viet Nam. Technical video on commercial and industrial rooftop solar systems in Vietnam — background material only, it does not replace the provisions of Decree 58/2025/ND-CP.

The 20% figure follows statements and guidance published on moit.gov.vn; conditions, pricing and procedures for surplus purchase follow the applicable regulations and are not an Orca Energy commitment.

04

What typically delays approval

  • Sizing capacity above on-site demand, creating export that is not permitted.
  • Ignoring limits of the existing meter and connection voltage level.
  • Construction and fire safety records not updated for the rooftop addition.
  • Missing equipment documentation (certificates, inverter data) in the first submission.
  • Discovering only during construction that development registration was required.

Frequently asked questions

Does a factory rooftop system need a permit?

Depending on capacity and connection mode, it may require only a notification or a development registration under Decree 58/2025/ND-CP. In all cases construction, electrical safety and fire safety rules apply, and the local utility must be involved whenever the system connects to the grid.

Can surplus solar be sold to EVN?

Per guidance published by MOIT, self-production, self-consumption systems may sell surplus electricity up to 20% of generated output under the applicable rules. Conditions, price and procedure depend on the legislation and the agreement with the utility.

What is zero export and when is it needed?

It is a control scheme that limits or fully blocks power flowing back to the grid, used when the system only serves on-site load or when the utility requires no export. Decree 243/2026/ND-CP added the concept of a Zero-Export device to the regulations.

How long does the process take?

It depends on the applicable route, the quality of the submission and the workload of the local utility. The most effective way to shorten it is to identify the correct route early and submit a complete technical package the first time.

Related guides

Sources

This guide compiles reference information from legal documents and official sources; it is not legal advice. Technical and financial ranges are industry reference values — project decisions require a site-specific survey.

Need a solar plan for your plant?

Orca Energy surveys the roof, analyses the load profile, simulates yield and builds the financial case for all three routes: self-investment, ESCO and renewable purchase through DPPA.

0867 831 368•solar@orcaenergy.vn

Request a consultation