Commercial rooftop solar in Vietnam: rules and delivery
Solar knowledge
Rooftop solar is the most practical way for factories, warehouses and retail sites in Vietnam to cut electricity costs, because it uses existing roof area and consumes the energy on site. This guide covers the current legal framework, how to size a system against the load curve, realistic yields in Vietnam and the EPC delivery sequence.
In this guide
01
Why rooftop solar fits industrial sites
The economics of rooftop solar come from self-consumption: every kWh generated and used on site replaces one kWh bought from the grid at the industrial or commercial retail tariff, so returns are highest when daytime load overlaps with solar hours.
Factories, cold stores, textile, plastics and steel plants and shopping centres usually have large roofs, adequate structural capacity and stable daytime load — exactly the conditions for a high self-consumption ratio without relying on exports.
- Lower energy cost at the retail tariff applied to production and commercial customers, especially in daytime peak blocks.
- A hedge against retail tariff increases across the 20–25 year life of the system.
- Verifiable renewable generation data for ESG reporting, GHG inventories and group-level RE100 roadmaps.
- Lower roof surface temperature under the module field, improving working conditions below.
02
Current rules: self-production and self-consumption under Decree 58/2025/ND-CP
Rooftop solar for self-production and self-consumption is governed by Decree 58/2025/ND-CP (effective 3 March 2025), which details the Electricity Law on renewable and new energy development. Read it before fixing capacity and the grid connection approach.
- Buildings that comply with investment, construction, land, environmental, safety and fire-protection rules may install rooftop solar for self-production and self-consumption.
- Systems connected to the national grid may sell surplus energy, but not more than 20% of the energy generated at the source output (measured at the inverter output, including energy passing through storage if any).
- The surplus purchase price is the previous year's average market energy price published by the system and market operator, capped by the maximum of the corresponding generation price bracket.
- Documentation, development procedures, connection agreements and commissioning follow the Decree and guidance from MOIT and EVN.
Legal content is reference information as of the publication date and does not replace project-specific legal advice.
03
Size the system against the load, not the roof area
A common mistake is sizing by available roof area. The correct approach is to analyse 15-minute interval data or 12 months of bills to find the capacity at which almost all generation is consumed on site, minimising exports.
- Collect hourly/daily load data and separate working days, weekends and holiday shutdowns.
- Simulate yield with local irradiation data (PVsyst) and overlay it on the daytime load curve.
- Check roof load capacity, sheet age, orientation and pitch, and shading from stacks, cooling towers and neighbouring roofs.
- Where load is concentrated at night or drops at weekends, consider adding BESS instead of more modules.
04
Realistic yields in Vietnam and what erodes them
Specific yield for rooftop systems in Vietnam typically falls in the range of roughly 1,100–1,400 kWh per kWp per year — higher in the south-central region, the Central Highlands and the south, lower in the north. Reference irradiation data is available from the World Bank Group's Global Solar Atlas.
- Module degradation over time (commonly published at around 0.4–0.55% per year depending on product and warranty).
- Temperature losses, soiling, partial shading and losses in cabling and transformers.
- Output curtailment from zero-export settings when the system is designed purely for self-consumption.
- Downtime for maintenance, grid outages or adverse weather.
These ranges are industry reference values for preliminary studies; committed yields must come from a simulation of the actual site, layout and equipment.
05
Delivery sequence with an EPC contractor
- Step 1 – Survey and data analysis: roof, structure, existing electrical system, load profile, connection point.
- Step 2 – Design and simulation: module layout, single-line diagram, inverter selection, yield and financial modelling.
- Step 3 – Documentation: filings under Decree 58/2025/ND-CP, connection agreement, fire protection, construction insurance.
- Step 4 – Construction and commissioning: installation, testing, trial run, acceptance and energisation.
- Step 5 – O&M and monitoring: remote performance monitoring, module cleaning, preventive maintenance, monthly performance reporting.
Frequently asked questions
Can a company export surplus rooftop solar to the grid?
Yes. For self-production and self-consumption systems connected to the national grid, surplus energy may be sold but not more than 20% of the energy generated at the source output under Decree 58/2025/ND-CP; the price is the previous year's average market energy price, capped by the maximum of the corresponding generation price bracket.
How much capacity should a factory install?
Optimal capacity comes from the daytime load curve, not the roof area; the goal is a high self-consumption ratio with minimal export. A plant running continuously during daylight hours typically absorbs the output of a system sized near its daytime base load.
Can solar be installed on an ageing metal roof?
It requires an assessment of load capacity, sheet thickness and age, and purlin condition. If the roof is near the end of its life, replace it first — removing and reinstalling an array later costs far more than replacing the roof up front.
Does rooftop solar count towards ESG and RE100?
Self-consumed renewable generation is used in GHG inventories and ESG reporting. RE100 recognition depends on the programme's criteria and documentation, typically requiring metering data and/or renewable energy certificates such as I-REC.
Related guides
Investment models
Zero-capex solar (ESCO): how the model works
How the solar ESCO model works: an investor funds the rooftop system, the company buys on-site power below the grid tariff. Eligibility, contract structure, risks and the clauses to negotiate.
Investment analysis
Solar investment cost and how to calculate payback
The cost structure of a rooftop solar project, what moves the cost per kWp, and how to calculate payback and levelised cost of electricity (LCOE) from simulated yield and grid tariffs.
EPC services
Solar EPC: scope of work and how to select a contractor
What a solar EPC contractor delivers: the E–P–C scope, the process from survey to commissioning and O&M, selection criteria and the contract risks that matter most.
Sources
- Decree 58/2025/ND-CP on renewable energy development – National legal database
- Vietnam Electricity (EVN)
- Ministry of Industry and Trade (moit.gov.vn)
- Global Solar Atlas – World Bank Group
- RE100 – Climate Group
This guide compiles reference information from legal documents and official sources; it is not legal advice. Technical and financial ranges are industry reference values — project decisions require a site-specific survey.