Orca EnergyORCA ENERGYCLEAN Energy for the Future

Zero-capex solar (ESCO): how the model works

Investment models

"Zero-cost solar" is the common name for the ESCO model: an investor funds the entire system on the company's roof, and the company pays only for the electricity it consumes, at an agreed rate below the grid tariff. This guide explains the mechanics, eligibility and the clauses to review before signing.

01

How the ESCO structure works

The ESCO model separates three roles: the roof owner (the electricity user), the investor or financier (owner of the system during the contract term), and the EPC/O&M contractor. The company pays for metered energy consumed, with no upfront capital outlay.

  • The investor funds equipment, construction, insurance and operation throughout the term (commonly 10–20 years depending on structure).
  • The company pays a per-kWh rate below the equivalent grid tariff, measured through a dedicated meter.
  • At the end of the term the system is usually transferred to the roof owner at a nominal price, or the parties extend the agreement.
  • Systems are normally designed to prioritise on-site consumption and minimise export, which protects the economics for both sides.

02

What makes a site bankable for an ESCO investor

  • Sufficient usable roof area in good structural condition; larger systems support more competitive tariffs.
  • Stable daytime load and a high self-consumption ratio — the single most important screening criterion.
  • Clean site documentation (land use rights, construction permit, fire protection) and a lease term longer than the ESCO contract.
  • Sound financial standing and payment history, because the investor takes credit risk on the offtaker.

03

Clauses that deserve careful negotiation

  • Tariff and escalation: the discount to the grid tariff and how it is adjusted when retail prices change.
  • Take-or-pay commitments: payment obligations if production slows or the plant shuts down for extended periods.
  • Responsibility for roof repairs, refurbishment or relocation of the array, and who bears removal and reinstallation cost.
  • Early termination conditions, buy-out price, and assignment rights if the company changes ownership.
  • Ownership of environmental attributes (I-REC certificates, carbon credits) — if needed for ESG or RE100, it must be explicit in the contract.

Rights to renewable energy certificates and carbon credits depend on the contract and applicable regulation; do not assume the electricity user automatically receives them.

04

ESCO, self-investment or DPPA?

  • Self-investment (CAPEX): lowest long-term levelised cost, but requires capital and in-house asset management.
  • ESCO: no capital required and immediate savings at the agreed tariff, in exchange for sharing long-term savings with the investor.
  • DPPA under Decree 57/2025/ND-CP: large-scale renewable purchase via the grid or a private line, suited to green energy demand beyond what a roof can deliver.
  • Many companies combine both: ESCO or self-investment on the roof, DPPA for the remaining renewable volume.

Frequently asked questions

Is zero-cost solar really free?

The company invests no capital but still pays for the electricity it consumes at the agreed rate. "Zero cost" means zero upfront investment, not free electricity.

How much below the grid tariff is an ESCO rate?

The discount is negotiated and depends on system size, self-consumption ratio, contract term, offtaker credit rating and the investor's cost of capital. There is no fixed discount that applies to every project.

How large does the roof need to be?

Larger projects are easier to finance; investors typically prioritise industrial roofs that can host roughly 500 kWp or more, equivalent to several thousand square metres of contiguous usable roof.

Who owns the system when the contract ends?

It depends on the terms. The common structure is transfer to the roof owner at a nominal price at the end of the term, but some contracts provide for extension or removal — read the asset transfer clause carefully.

Related guides

Sources

This guide compiles reference information from legal documents and official sources; it is not legal advice. Technical and financial ranges are industry reference values — project decisions require a site-specific survey.

Need a solar plan for your plant?

Orca Energy surveys the roof, analyses the load profile, simulates yield and builds the financial case for all three routes: self-investment, ESCO and renewable purchase through DPPA.

0867 831 368•solar@orcaenergy.vn

Request a consultation